Our Client approached us with a new build they were wishing to commence for their daughter and her family to the garden of their home in Highclere, just outside of Newbury, Berkshire.

We arrived on site on the 24th January 2017 and by the 3rd February 2017 (1 week and 3 days later!) we had the superstructure installed.

Below is a nice sequence of photos showing the very quick and efficient process we followed to ensure our Clients could book in their trades following us, so that the whole build ran to an efficient schedule.

The ground floor panels are installed and propped in place ready for the internal panels to be erected.

Once the internal ground floor panels are installed, along with the posi metal web joists and flooring, the external first floor panels were lifted on top ready for installation.

After all the first floor external and internal panels have been erected, the roof trusses are then ready to be fixed onto the top to form the roof structure.

The roof trusses are fully engineered and were also manufactured off-site. They were delivered direct to site and also installed by our erecting teams.

Once the superstructure is in place our erecting team then install firestops to all the window and door openings as well as up each corner of each of the elevations.

Once all the final snagging was completed, our works were done and it was ready for the other trades to start their works.

If you are interested in constructing your new home within a 2 week time schedule, contact us directly, sending your drawings to lucy@vision-dsl.com. Alternatively, you can use our contact form or just call 0118 971 2181.